Grading • paving • Underground Projects

  • Peoria Audi Showroom & Service Building - Peoria, Arizona

    Peoria Audio

    Peoria Audi

    Johnson Carlier

    Project Name: Peoria Audi Showroom & Service Building
    Owner: Van Chevrolet of Phoenix LLC
    Client: Johnson Carlier
    Completion Date: November 2010
    Engineer: Multatech Architects & Engineers
    Project Description: KEAR is provided grading and underground utility installation services for the construction of a new Audi Dealership on Bell Road in Peoria, Arizona. KEAR’s scope of work included mass earthwork, onsite and offsite utility installation, and building sub-grade prep. The project is scheduled for completion in November of 2010.
     
  • U-Haul Storage Center - Gilbert, Arizona

    U-Haul Storage Center

    U-Haul Storage Center

    Sea Con LLC

    Project Name: U-Haul Storage Center
    Owner: UHC of Eastern Arizona
    Client: Sea Con LLC
    Completion Date: October 2010
    Engineer: CLC Associates & Robert Kubicek Architects
    Project Description: KEAR is providing turn-key grading, paving and underground utility installation services for the construction of a new U-Haul storage facility in Gilbert, Arizona. The project involves over 4,500 cy of site cut/fill and 1,600 sy of gravel pave & decomposed granite. KEAR is also installing all water, fire, storm and sewer lines that will serve the new facility. As a subcontractor to the prime contractor Sea Con LLC, KEAR is providing the client with a one-stop shop for their complete site-work and wet utility scopes. The project is scheduled for completion in October of 2010.
     
  • Chase Bank - Scottsdale & Thomas - Scottsdale, Arizona - $200,000

    Chase Bank

    Chase Bank

    Midwest General of Arizona

    Project Name: Chase Bank – Scottsdale & Thomas Roads
    Owner: JP Morgan Chase
    Client: Midwest General of Arizona
    Completion Date: February 2010
    Contract Size: $200,000
    Engineer: Nudell Architects
    Project Description: KEAR provided grading, paving and underground utility installation services for the construction of a new Chase Bank on Scottsdale Road and Thomas in Scottsdale, Arizona. KEAR’s scope of work included mass earthwork, onsite and offsite utility installation, building sub-grade prep, and paving. The project included temporary closure of portions of Scottsdale Road for the installation of new offsite storm drain lines and fire lines. The project was completed on schedule in February of 2010.
     
  • Chase Bank - Mill Ave & University - Tempe, Arizona - $150,000

    Chase Bank

    Chase Bank

    Midwest General of Arizona

    Project Name: Chase Bank – Mill Avenue & University
    Owner: JP Morgan Chase
    Client: Midwest General of Arizona
    Completion Date: May 2010
    Contract Size: $150,000
    Engineer: Nudell Architects
    Project Description: KEAR is providing complete earthwork and utility construction services for a new Chase Bank being constructed on Mill Avenue and University in downtown Tempe, Arizona. KEAR’s scope of work includes earthwork, onsite and offsite utility installation, primary and secondary power trenching, and paving. The project included temporary closure of portions of Mill Avenue for the installation of new water, fire, sewer and storm lines. The project is scheduled for completion in May of 2010.
     
  • Chase Bank – Happy Valley & I-17 - Phoenix, AriZona - $60,000

    Chase Bank

    Chase Bank

    Midwest General of Arizona

    Project Name: Chase Bank – Happy Valley & I-17
    Owner: JP Morgan Chase
    Client: Midwest General of Arizona
    Completion Date: November 2009
    Contract Size: $60,000
    Engineer: Nudell Architects
    Project Description: KEAR is pleased to be performing our first project with Midwest General of Arizona (MWGAZ), which is the construction of a new Chase Bank in north Phoenix. MWGAZ has subcontracted KEAR for the on site grading, paving and utility construction services. KEAR’s scope includes clearing/grubbing, mass earthwork, utility installation, building sub-grade prep, and paving. KEAR’s underground utility package includes all water, storm, sewer, and fire lines. The project is a Fast Track project with completion scheduled for late November 2009.
     
  • Mountian America Credit Union - Mesa, Arizona - $189,000

    Mountian America Credit Union

    BCI

    Project Name: Mountain America Credit Union - Mesa
    Owner: Mountain America Credit Union
    Client: Building Committee, Inc (BCI)
    Completion Date: July 2009
    Contract Size: $189,000
    Engineer: Woods– Associates, Inc
    Project Description: BCI has subcontracted KEAR for the on site grading, paving and utility construction services for a new Mountain America Credit Union on Southern and Greenfield in Mesa, AZ. KEAR is providing site development services including clearing/grubbing, mass earthwork, utility tie-in’s, building sub-grade prep, on-site retention excavation, and paving. KEAR’s underground utility package includes all water, storm, sewer, and fire lines.
     
  • Desert Breeze Pipeline - Chandler, Arizona - $287,000

    Desert Breeze Pipelin

    Desert Breeze Pipeline

    Chandler

    Project Name: Desert Breeze Pipeline
    Owner: City of Chandler
    Client: City of Chandler
    Completion Date: March 2009
    Contract Size: $287,000
    Engineer: Burns & McDonnell
    Project Description: KEAR was contracted to complete a domestic waterline project for the City of Chandler near the intersection of Desert Breeze and Rural Roads in Chandler, AZ. The project is a design build, and KEAR’s management team brought Burns & McDonnell on board to complete the engineering services for the project. KEAR’s previous project experience with Burns & McDonnell proved valuable to providing the City of Chandler with a complete design and construction package. The project involves the installation of 8” and 12” waterlines, including the crossing of Rural Road and various tie-in locations including an existing well site and reservoir. The project was completed in March of 2009.
      Burns & McDonnell
     
  • Maverick Masonry Corporate Office Building - El Mirage, Arizona - $290,000

    Maverick Masonry Corporate Office

    Maverick Masonry Corporate Office

    Tieman Corp

    Project Name: Maverick Masonry Corporate Office Building
    Owner: RGT Tieman Northern LLC
    Client: The Tieman Corp, Inc.
    Completion Date: July 2009
    Contract Size: $290,000
    Engineer: Cottrell Engineering Corp - Civil
    Project Description: The Tieman Corporation has subcontracted KEAR to provide grading, paving and underground utility construction services for the new Maverick Masonry Office building in El Mirage, AZ. KEAR is installing all domestic water, fire, storm drain, and sewer utilities, along with all site earthwork and grading, including site clearing, grading, excavation of the building basement, and removal of 2,500 cubic yards of spoils. KEAR is also providing sub-grade prep for the new paver driveway and parking lot, along with over 25,000 square feet of asphalt pavement.
     
  • Chandler Alternative School - Chandler, Arizona - $360,000

    Chandler Alternative School

    Chandler Alternative School

    Concord

    Project Name: Chandler Alternative School
    Owner: Chandler Unified School District
    Client: Concord General Contracting
    Completion Date: May 2009
    Contract Size: $360,000
    Engineer: Hubbard Engineering (Civil) & NTD Architecture
    Project Description: Concord General Contracting has subcontracted KEAR for the on and off-site grading and paving services for a new 25,554 SF Alternative School in Chandler, AZ. KEAR is providing site development services including demolition, clearing/grubbing, mass earthwork, off-site improvements to Cooper and Frye Road, building sub-grade prep, on-site retention excavation, and installation of an asphalt fire loop and parking lot. KEAR is scheduled to complete the site-work in November of 2009.
     
  • Arizona Federal Credit Union - Phoenix, Arizona - $360,000

    BCI

    Project Name: Arizona Federal Credit Union - Washington Branch
    Owner: Arizona Federal Credit Union
    Client: Building Committee, Inc (BCI)
    Completion Date: May 2009
    Contract Size: $360,000
    Engineer: Woods– Associates, Inc
    Project Description: BCI has subcontracted KEAR for the on and off-site grading, paving and utility construction services for a new Arizona Federal Credit Union on 44th St and Van Buren in Phoenix, AZ. KEAR is providing site development services including clearing/grubbing, mass earthwork, off-site improvements to Van Buren, off-site utility tie-in’s, building sub-grade prep, on-site retention excavation, and drywell installation. KEAR’s underground utility package includes all water, storm, sewer, fire and pneumatic bank teller system trenching.
     
  • Walgreens at Casa Grande Plaza - Casa Grande, Arizona - $1,000,000

    Walgreens at Casa Grande Plaza

    Walgreens at Casa Grande Plaza

    Walgreens at Casa Grande Plaza

    Project Name: Walgreens at Casa Grande Plaza
    Owner: Steve Johnson Development
    Client: Wilger Enterprises
    Completion Date: April 2009
    Contract Size: $1,000,000
    Engineer: KPFF Engineers and George Rainhart
    Project Description: KCC is performing 7.5 acres grading and site-work including 2700lf of fireline, 3000lf of 72” CMP, and 70,000sf of paving and base for a new Walgreens and two retail shops in Casa Grande, Arizona. KEAR is performing the work as a subcontractor to Wilger Enterprises.
     
  • Glendale Spring Training Facility - Glendale, Arizona - $600,000

    Glendale Spring Training Facility

    Glendale Spring Training Facility

    Glendale Spring Training Facility

    Project Name: Glendale Spring Training Facility
    Owner: LA Dodgers & Chicago White Sox
    Client: MA Mortenson
    Completion Date: January 2009
    Contract Size: $600,000
    Engineer: HKS
    Project Description:

    KEAR is providing structural excavation and backfill services for the new Glendale spring training facility located at 107th Avenue and Camelback. The new facility is the future home of the Chicago White Sox and LA Dodgers. KEAR's scope of work was completed in November of 2008.

    View Letter

     
  • Western Valley Childcare - Surprise, Arizona - $600,000

    Western Valley Childcare

    Western Valley Childcare

    Smith Construction Services

    Project Name: Western Valley Childcare
    Client: Smith Construction Services
    Completion Date: April 2008
    Contract Size: $600,000
    Engineer: Hess Rountree
    Project Description: KEAR has been subcontracted by Smith Construction Services to provide mass grading and underground utility construction for the new Western Valley Childcare facility in Surprise, Arizona. KEAR’s subcontract consists of approximately 6 acres of grading, 3,800 lf of fireline, 1,130 lf of sewer line, and 600 lf of storm lines.
     
  • Gas Sleeve - Reems & Waddell - Surprise, Arizona - $25,000

    Gas Sleeve Project

    Gas Sleeve Project

    Project Name: Gas Sleeve Project - Reems & Waddell
    Client: CAP II
    Completion Date: September 2007
    Contract Size: $25,000
    Engineer: Southwest Gas
    Project Description: KEAR was subcontracted by CAP II to install a new gas line sleeve for southwest gas. The project consisted of 300+ lf of asphalt sawcut, removal, sleeve installation, and patch.
       Southwest Gas
     
  • Goodyear Community Park I - Goodyear, Arizona - $850,000

    Goodyear Community Park

    Goodyear Community Park

    Goodyear Community Park

    Project Name: Goodyear Community Park Phase I
    Owner: City of Goodyear, Arizona
    Client: Norquay Construction
    Completion Date: January 2008
    Contract Size: $850,000
    Engineer: URS
    Project Description: KEAR has been subcontracted by Norquay Construction Inc. to provide mass grading and underground utility construction for the new City of Goodyear community park. KEAR’s sub-contract consists of approximately 17 acres of grading, 2,500lf of fireline, and 3,000lf of sewer line.
      Norquay Construction City of Goodyear
     
  • Mesquite Elementary Phase II - Glibert, Arizona - $500,000

    Mesquite Elementary

    Mesquite Elementary

    Gilbert

    Project Name: Mesquite Elementary
    Owner: City of Gilbert, Arizona
    Client: Gilbert Unified School District
    Completion Date: April 2007
    Contract Size: $500,000
    Engineer: H.D.A. Architects
    Project Description: For the second phase classroom expansion of the Mesquite Elementary school, KEAR provided site grading, paving and underground utility construction services. This project in-cluded 2,000lf of wet utilities, 3,900 cy of import, 4,200 cy of export, and 35,000sf of asphalt paving.
     
  • Copper Star Bank - Peoria, Arizona - $150,000

    Copper Star Bank

    Copper Star Bank

    Copper Star Bank

    Project Name: Copper Star Bank
    Owner: Copper Star Bank
    Client: Keegan Builders
    Completion Date: April 2007
    Contract Size: $150,000
    Engineer: BCA Engineering
    Project Description: KEAR was subcontracted by Keegan Builders to provide underground utility construction for the new Copper Star Bank in Peoria, Arizona. KEAR’s subcontract consisted of the complete installation and testing of all underground wet utilities, both on and offsite.
     
  • M&I Bank - Mesa, Arizona - $130,000

    M&I Bank

    Project Name: M&I Bank
    Owner: M&I Bank
    Client: Keegan Builders
    Completion Date: January 2006
    Contract Size: $130,000
    Engineer: BCA Engineering
    Project Description: KEAR was subcontracted by Keegan Builders to provide mass grading and underground utility construction for the new M&I Bank in Mesa, Arizona. KEAR’s subcontract consisted of the complete existing site demolition, installation and testing of all underground wet utilities, both on and offsite.
     
  • Walgreens #9057 - Phoenix, Arizona - $250,000

    Walgreens

    Walgreens

    Walgreens

    Project Name: Walgreens #9057
    Owner: Walgreens Inc
    Client: Wilger Enterprises
    Completion Date: July 2005
    Contract Size: $250,000
    Engineer: Broadbent & Associates
    Project Description: KEAR provided onsite earthwork construction services for the new Walgreens store at Union Hills and 19th Ave in North Phoenix. KEAR’s scope of work included all site demo and clearing, mass grading, pad prep, and asphalt paving.
      Walgreens Wilger Enterprises
     
  • Apache Campus Parking Lot - Scottsdale, Arizona - $130,000

    Apache Campus Parking Lot

    Apache Campus Parking Lot

    Project Name: Apache Campus Parking Lot
    Owner: Scottsdale Unified School District
    Completion Date: September 2005
    Contract Size: $130,000
    Engineer: Hess-Roundtree
    Project Description: KEAR completed the installation of a 50,000 SF parking lot for the Scottsdale Unified School District. This project included complete site construction services including clear/grub, storm-drain/retention, sub-grade prep, asphalt placement, finishes and striping.
      Scottsdale Unified School District