Lake Havasu City, AZ-Mulberry WWTP Tertiary Filter Capacity Increase design-Build

Project Owner
Lake Havasu City
Project Location
Lake Havasu City, Arizona
Project Delivery Method
Design-Build
Project Details
KEAR provided complete design-build services to upgrade two existing tertiary filters and add another to the existing filter train at the Lake Havasu Mulberry WWTP. The project included the relocation of two existing Schreiber Fuzzy Filters to allow for the installation of a third new filter in the filter train. The existing containment area required structural modifications to accommodate the new filter and the existing electrical and control systems were also upgraded. KEAR also performed mechanical upgrades to the two existing filters, including replacing the existing internal traveling plates, re-coating the vessel interiors, and installing new turbidity meters. The project was phased to allow the plant to continually operate with full filtration capabilities while the systems were upgraded.