Project Owner

City of Torrance, California

Project Location

Torrance, CA

Project Delivery Method

Design-Bid-Build

Project Details

KEAR provided prime contractor construction services on the Sodium Fluoride Feed system project for the City of Torrance, California. The project was located at two separate locations within the City of Torrance; The Robert W. Goldsworthy Desalter facility, and Well No. 9. KEAR is installed skid mounted fluoride feed systems at each location, including chemical feed pumps, drive motors, control panels and SCADA system upgrades. Supporting infrastructure for the new systems were also installed including new injection and feed piping, support slabs, and general site work improvements.